4 Workflow 4 - 1 Workflow The replacement procedure with NB-V1 is as follows. Operations in are explained from the next page.
4-2 Preparation 4-2-1 Confirmation of replaceability 4-2-2 Uploading the project from the existing NB 4-2-3 Converting the project for NB-V1 4 -3 Removing the currently installed NB 4-3-1 Turning OFF the power to the currently installed NB 4-3-2 Removing all cables 4-3-3 Removing the storage devices 4-3-4 Removing the currently installed NB from the operation panel 4-4 Installing NB-V1 4-4-1 Installing the NB-V1 to the operation panel 4-4-2 Wiring the cables 4-4-3 Installing the storage devices 4-5 Start-up 4-5-1 Turning ON the power to the NB-V1 4-5-2 Downloading the project to the NB-V1 4-5-3 Checking the settings and communications 4-5-4 Starting operation 14