Kaiyi D375A-6 — Assembly procedure, necessary equipment, and schedule

Assembly procedure, necessary equipment, and schedule The F/D assembly and pivot shaft are assumed to be installed to the body beforehand. Any change of the schedule caused by weather is not included. Special field work shall be arranged separately.

Schedule 4 4th day 8:00 10:00 12:00 14:00 16:00 18:00 Test operation and adjustment Washing, touching up, painting Unnecessary 8H 3 workers 24H 112H 3rd day 8:00 10:00 12:00 14:00 16:00 18:00 Installing tracks Installing blade Connecting hoses Installing cab Installing ROPS guard 25-ton wrecker 1 unit × 8H 3 workers 24H Grand total 2nd day 8:00 10:00 12:00 14:00 16:00 18:00 Installing T/F Adding and checking oil Installing ripper sub-assembly 50-ton wrecker 2 units × 8H 4 workers 32H 1st day 8:00 10:00 12:00 14:00 16:00 18:00 Unloading trailer Installing pivot shaft and blade lift cylinder Installing under cover Assembling blade sub-assembly 50-ton wrecker 2 units × 8H 4 workers 32H Trailer must arrive at field before 8:00.

Wrecker Working hours Number of workers Total man-hours