24. SERVICE PROCEDURE 24.5 EVERY 100 HOURS SERVICE Maintenance for every 50 hours should be carried out at the same time. 24.5.1 LUBRICATING NOTICE Carry out greasing of greasing point 1-7 every 10 hours for the first 100 hours on a new machine. After digging under water, be sure to supply grease to the pins which were submerged. 1. Set the work equipment in the greasing posture below, then lower the work equipment to the ground and stop the engine. 2. Using a grease pump, pump in grease through the grease fittings shown by arrows. 3. After greasing, wipe off any ol grease that was pushed out. 1. Boom cylinder foot pin (2 points) 2. Boom foot pin (2 points) 3.
Boom cylinder rod end (2 points) 4. Arm cylinder foot pin (1 point) PC130/150LGP-6K ENG 3-47