Downloaded from https://www.everyspec.com MIL-STD-3001-4(AS) f. Additional WPs within the same manual that are required to complete the task or discussion shall be presented first in numerical sequence. The WP title and WP number shall also be identified. The publication number is not required. g. Referenced publications not prepared in WP format shall be presented in numerical sequence. The title and publication number shall also be included. 5.2.2.2 Record of Applicable Technical Directives . Technical directives applicable to a specific work package shall be listed in a record of applicable technical directives list (standard list) .
If no technical directives apply, the heading "Record of Applicable Technical Directives" shall be omitted from the work package. The record of technical directives shall be prepared in accordance with the following guidelines. a. All issued technical directives having any impact on the WP shall be listed upon incorporation into the WP. b. Approved engineering change proposals (ECPs) that have no effect on retrofit of the end item shall not be listed in the record of applicable technical directives (e.g., "no technical directive will be issued"). c. All technical directives and related ECPs or Rapid Action Minor Engineering Changes (RAMECs) shall be listed upon incorporation into the WP.
(1) "TD Type/No." - Enter the type and number of the technical directive, e.g., "A6 AFC 454" or "AVC 1492." Note: The "TD Type/No." is identified on the Change Control Board (CCB) formal letter of ECP or RAMEC approval. Refer to NAVAIR 00-25-300. (2) "TD Date" - Enter the date of issue of the technical directive. If the number of the technical directive has been assigned but the directive has not been issued, a dash (-) shall be entered. (3) "Title and ECP/RAMEC No." - The title of the technical directive and the ECP number or RAMEC, if applicable, shall be listed.
If a technical directive listed is the direct result of an approved ECP or RAMEC, the acronym ECP or RAMEC and number shall be shown in parentheses following the technical directive title. (4) "Date Inc." - The date the information affected by the technical directive or the ECP was incorporated into the WP.
(a) If the technical directive number has been assigned and the directive has not yet been issued (retrofit program), but the ECP that incorporates the change in the production program has been approved, the production ECP coverage shall be included, and the notation "Production coverage only" shall be entered under "Remarks." (b) When the retrofit TD is approved and incorporated in a change or revision following the incorporation of the production ECP coverage, the TD date of issue shall be entered under "TD Date," the notation "Production coverage only" shall be removed from under "Remarks," and the date of retrofit coverage incorporation shall be listed under "Date Inc." (in lieu of the production ECP coverage incorporation date).
(5) "Remarks" - Enter any applicable remarks. 4