omron — 3-1 Installation

3 Installation and Wiring z Mounting NB Unit to Control Panel Install the NB Unit by embedding it into the operation panel. Use the panel mounting brackets and Phillips screwdriver installation. Proceed the installation following the procedures below. 1 Panel cutout with dimensions is shown below. Fit the NB Unit into the panel from the front side.

Width 3-1 Installation Opening dimensions Height 3 NB5Q-TW00B/TW01B 172.4(+0.5/-0) Ї 131.0(+0.5/-0) NB3Q-TW00B/TW01B 119.0(+0.5/-0) Ї 93.0(+0.5/-0) NB7W-TW00B/TW01B 191.0(+0.5/-0) Ї 137.0(+0.5/-0) NB10W-TW01B 258.0(+0.5/-0) Ї 200.0(+0.5/-0) 2 As follows, insert the panel mounting brackets at the locations indicated by red box around the back of the NB Unit. Insert the hooks of positioners into the square holes on the Unit to hold the fixators properly, and tighten the screws firmly with the screwdriver. z NB5Q/NB7W-TW …… B NB-series Programmable Terminals Startup Guide Manual(V109) 3-3 Models Opening Dimension (W¯H mm)