SAMI G S 8.2 Sequence of Operations PREPARATION - familiarisation with safety instructions SAFETY PRECAUTIONS INSTALLATION INSPECTION - earthing - supply and motor cables - control cables - availability and quality of cooling air etc. START-UP START-UP DATA PARAMETERS - checking and completing the Start-Up Data parameter values KEYPAD CONTROL TEST WITHOUT MOTOR - checking the operation of SAMI without motor KEYPAD CONTROL TEST WITH MOTOR - checking the operation of SAMI with motor - checking external controls - checking emergency stop (if installed) Figure 8-1. The sequence of operations during commissioning.
More detailed information describing the necessary functions in each block is given on pages 29 - 32. 30