sinee — 5.1 Commissioning process

A90 series Inverter User Guide 5 Quick start commissioning 5.1 Commissioning process Start According to Chapter 2 and 3 to install the inverter and complete the wiring Ensure the safety and check wiring before power up (Section 5.2) Confirm the status of inverter is correct after power up (Section 5.3) If there are available application macros, select the application macros first (Section 5.4) Enter the motor nameplate parameters, perform motor parameter autotune (Section 5.7) Set process parameters (Section 5.6) control method V/F control Set F05 parameter group F00.01=0 F00.01=1 F00.01 Vector control Set F06 parameter group The default parameters generally meet the requirements Keypad control no-load operation, to confirm the direction of the motor and the system mechanical action are correct Modify F00.02 for the required command source, no-load operation, to confirm the system mechanical action is correct Running with load to confirm whether the operation meets the requirements the end Figure 5-1 Commissioning process 26