Komatsu — MEASUREMENT OF SOLENOID VALVE OUTPUT PRESSURE

TESTING AND ADJUSTING MEASUREMENT OF SOLENOID VALVE OUTPUT PRESSURE MEASUREMENT OF SOLENOID VALVE OUTPUT PRESSURE Solenoid valve output pressure measurement tools Measure solenoid valve output pressure after confirming that control circuit original pressure is normal. 2. Fit fitting L2 and connect hoses (1) through (6) again. k Lower the work equipment to the ground and stop the engine. After the engine stops, operate the control lever several times to release the re- maining pressure in the piping. Then loosen the oil filler cap to release the pressure inside the hy- draulic tank. 3. Fit fitting of hydraulic tester L1 and connect it to oil pressure gauge .

Use an oil pressure gauge with the capacity of 5.9 MPa{60 kg/cm 2 }. 1. Disconnect the hoses of solenoid valve to be measured at the outlet side. Hose (1) is installed at the rear of operator's cab, and hoses (2) through (6) are installed at the center of revolving frame. 4. Start the engine and keep it running until the hydraulic oil temperature rises to the operating range. PC210/240-7K 20-135 Mark Part No. 799-101-5002 Part Name Hydraulic Tester L 1 790-261-1203 Digital Type Hydraulic Tester 2 799-401-2910 Grease Fitting (Size 02) 07002-*1423 O-ring No.

Solenoid valve to be measured 1 PPC lock solenoid valve 2 Travel interconnection solenoid valve 3 Merge/divide solenoid valve 4 Travel speed shifting solenoid valve 5 Swing and parking brake solenoid valve 6 2-stage relief solenoid valve