— MIL-STD-3001-4(AS) — Digital Technical Information, Part 4 of 8 (2001) (EN)

Downloaded from https://www.everyspec.com MIL-STD-3001-4(AS) c. Procedures or practices that, if not correctly followed, could result in injury to personnel, damage or destruction to the equipment, or improper system operation shall be highlighted by warnings, cautions, and notes. d. Appropriate warnings shall be included when hazardous chemicals and adverse health factors in the environment cannot be eliminated. Such warnings shall be identified by the related approved icon. Complete warnings shall be provided in the HMWS pages for each hazardous material used in the manual. e. Torque requirements, values, and sequences shall be indicated.

Torque values shall be given for all structural attaching hardware, fluid couplings (fuel, oil, hydraulic, pneumatic, etc.), and connections. Torque values shall include torque correction factors as in crowfoot extensions, thread lubricants, cadmium-plated screws, etc. Torque values identified in the tasks must reflect torque wrenches authorized. Upon completion of torque action, instructions shall be included for any additional action, such as use of an orientation mark. f. Such terms as "reverse removal procedure" or "assemble in reverse order of disassembly" shall not be used in any maintenance task. g.

Maintenance procedures or steps that are essential to equipment performance or safety of personnel are considered to be Quality Assurance procedures and shall be highlighted by the addition of the abbreviation "(QA)" following the procedure/step. The last procedural step of a procedure shall reference the next required action to ensure that all required tasks, including final testing of the end item (verification of repair), are accomplished prior to completion of work. 5.3.1.1.2 Preparation for use and assembly. a.

As applicable, special procedures shall be prepared for unpacking, removing protective coatings, depreservation, and setting up equipment furnished in a partially assembled state. When the equipment is intended to be anchored or mounted in a fixed location and installed by a supporting facility, installation procedures are not required. If containers are to be used again, kept for future use, turned in to supply, or require special disposition method, the necessary procedures shall be prepared. b. Assembly, pre-installation and installation procedures shall be prepared when needed. These instructions shall be supported by illustrations.

When applicable, instructions for preoiling and preparation for initial run for engines shall be included. All information required to make the equipment fully operable shall be included. Instructions for cabling or plumbing that must be made up from bulk items, tests required during installation, power requirements, connections, and initial control settings needed for installation purposes shall be prepared. A reference to the operational checkout of the equipment shall be included for Quality Assurance. 5.3.1.1.3 Handling. 5.3.1.1.3.1 Handling.

Instructions and precautions for ground handling of the aircraft/equipment under adverse conditions such as extreme cold, heat, humidity, dust, and high winds shall be prepared. Instructions for handling, loading and unloading, moving, mooring, including tie-down in high winds and sea state, shall be included. Specific wind velocities that could damage the aircraft shall be identified. The following ground handling procedures shall be provided, as applicable. For the purposes of the transportation of aircraft, procedures for the loading and unloading of aircraft into approved cargo aircraft or other applicable means of transportation shall be developed.

Procedures to prepare the aircraft for 9