Freightliner — Century Class Maintenance Manual

Exhaust 49 4. Remove the CGI piping between the engine and aftertreatment device (ATD). 1 2 5. On the workbench, remove the CGI bellows from the exhaust piping. Do not damage the piping. A NOTE: The following step, and its substeps, is to be done without the bellows installed. This will align the pipes so that the bellows can be installed correctly. 6. Install the CGI piping (without CGI bellows) and align piping. 6.1 Attach the aft CGI pipe to the ATD. 02/23/2011 f490457 6.2 Attach the forward CGI pipe to the en- gine. A. Measure the pipe gap. 1. CGI Aft Pipe 2.

CGI Forward Pipe NOTICE When the CGI pipes and bellows are installed, there should be approximately 3/4 inch (19 mm) clearance from the main bellows. Contact between the bellows could result in an exhaust leak, which in this case may allow ingestion of contaminants into the engine causing engine damage. Fig. 9, Measuring the Pipe Gap (typical) 9. Once the pipes are correctly aligned and sepa- rated at the correct distance, secure the aft CGI pipe to the ATD and to any CGI pipe support brackets. 10. Remove the forward CGI pipe from the truck. 6.3 Use a straightedge to align the pipes so that the pipe ends that attach to the bel- lows are parallel and concentric. 11.

Slide the slip clamp, with the retaining ring and graphite gasket ring, on the aft CGI pipe. See Fig. 10 for proper installation. NOTICE 2 3 4 When shortening the CGI pipe(s), it is critical to leave a minimum of 1 inch (25.4 mm) of straight pipe on the end of each CGI pipe to allow for pipe insertion and clamp clearance. Failure to do this could result in an exhaust leak, which in this case may allow ingestion of contaminants into the en- gine causing engine damage. 7. Once the pipes are aligned, measure the pipe gap between the CGI pipes and record the dis- tance. See Fig. 9 , Ref. A. The existing pipe gap is designed at 10 inches (254 mm).

A 10.75 inches (273 mm) pipe gap is required for the replacement CGI bellows and clamps. This requires one or both of the CGI pipes to be shortened. 01/29/2010 f490415 1. Aft CGI Pipe 2. Retaining Ring 3. Graphite Gasket 4. Slip Clamp 5. CGI Bellows 8. Using a yellow paint pen, mark the pipes 1.5 inches (38 mm) in from the end of each pipe. These two marks will be used to center the bel- lows between the two pipes. Fig. 10, Aft Facing Slip Clamp Installation 12. Slide the new bellows onto the aft CGI pipe as far as it will go. See Fig. 11 , Ref. A. Measure- ment A should be at least 7/16 inch (10 mm) past the face of the flange. Century Class Trucks Maintenance Manual, January 2016 49/5 1