www.WorkshopManuals.co.uk Dismantling and Assembly Auxiliary Relief Valves (ARV) and Load Hold Check Valves (LHCV) Assembly The numerical sequence shown on the illustration is intended as a guide to dismantling. Renew all 'O' rings and back-up rings. Lubricate parts with JCB Hydraulic Fluid before assembling. Make sure that all the parts move freely. For assembly the sequence should be reversed. The following points MUST be avoided when dismantling and assembling the valve: Fit back-up ring 13 on the upper side of 'O' ring 12 . CONTAMINATION DAMAGE TO SPOOL DAMAGE TO SEAL GROOVES Fit flat face of sleeve 9 against shoulder of poppet 10 .
Torque tighten item 14 using the special tool (see Service Tools ), until its shoulder seats firmly against item 1 . All or any of the above points may result in possible problems with the valve. Pressure test the relief valves, refer to Service Procedures, Loader Valve - Pressure Testing . The ARV's are identical in design but have different pressure settings, refer to Technical Data . Torque Settings Item Nm kgf m lbf ft 1 65 6.6 48 3 24 2.5 18 15 81 8.3 60 The LHCV's are identical. Dismantling When removing 'O' rings and seals, use an an appropriately rounded tool that WILL NOT cause any damage to the seal grooves. Discard ALL 'O' rings and back up rings. DO NOT use worn or damaged items.
Dismantle sub-assembly 14 from item 1 using a special tool (see Service Tools ). The special spanner locates in cross holes B . Make sure that small drilling A is not blocked. Ensure good condition of seating faces on poppet 18 and on the mating face of the valve block. Inspect the valve components for scratches, nicks or any other type of damage, replace with new if required. 9803/3280 Purchased from www.WorkshopManuals.co.uk Issue 1 Section E Hydraulics Section E 50 - 9 50 - 9 50 - 9 Loader Valve - Fixed Flow 50 - 9