www.WorkshopManuals.co.uk Dismantling and Assembly Bolt on Auxiliary Spool Section Auxiliary Relief Valve (ARV) The numerical sequence shown on the illustration is intended as a guide to dismantling. For assembly the sequence should be reversed. Great care should be taken when dismantling and assembling a valve to avoid the following:- Contamination Damage to spools Damage to seal grooves Any of the above may result in possible problems with the operation of the valve. When Dismantling When removing 'O' Rings and seals, use an appropriatly rounded tool that WILL NOT cause any damage to the seal grooves. Discard ALL 'O' Rings and back-up rings. DO NOT use worn or damaged items.
Inspection Inspect the valve components for scratches, nicks or any other type of damage, replace with new if required. When Assembling Renew all 'O' rings and back-up rings. Lubricate parts with JCB Hydraulic Fluid before assembling. Make sure that all the parts move freely. Make sure that the ‘O’ rings and back-up rings are fitted the correct way, items 13, 14 and 19, 20 . Adjust pressure setting as required, refer to Service Procedures, Pressure Testing - MRV and ARV’s .
Torque Settings Item Nm kgf m lbf ft 1 62 6.4 46 5 5.4 - 8.2 0.55 - 0.83 4 - 6 10 41 - 68 4.15 - 6.9 30 - 50 9803/3280 Purchased from www.WorkshopManuals.co.uk Issue 1 Section E Hydraulics Section E 50 - 27 50 - 27 50 - 27 Loader Valve - Fixed Flow 50 - 27