www.WorkshopManuals.co.uk Dismantling and Assembly - Power Sideshift Ram Assembly 1 Clean the threads of the end caps and cylinder using a wire brush. The numerical sequence shown on the illustration is intended as a guide to dismantling. 2 Use JCB Cleaner/Degreaser to ensure that all threads are free from grease, hydraulic oil and sealant. Allow 15 minutes for solvent to dry before applying JCB Threadlocker and Sealer (High Strength). For assembly the sequence should be reversed. Dismantling 1 Fix the ram assembly on a locally manufactured strip/rebuild bench as shown at A .
Ensure that lubricants used during assembly do not come into contact with the JCB Threadlocker and Sealer (High Strength). 2 Remove both end caps 1 , (46mm AF). Pull the piston rod assembly from the cylinder. 3 Refer to JCB Ram Sealing Procedure for the correct method of fitting seals to the end cap and piston head. Note 1: DO NOT allow the piston rod to come into contact with the cylinder bore. The cylinder bore may be damaged by careless dismantling. 4 Clamp the cylinder vertically and lower the piston rod assembly in from the top, as shown at B . Take care not to allow the piston rod to come into contact with the cylinder bore.
Be sure to engage the piston head new wear rings and seal carefully into the cylinder. If the piston head wear rings or seal are damaged during this stage, they must be renewed. 3 Position the piston rod assembly on a bench in place of the ram cylinder. Remove the wear rings 2 and seal 3 from the piston head. Note 2: The piston head cannot be removed from the rod. If there is damage to the rod or piston head, replace the complete assembly. 5 Fit new ‘O’ rings 8 to spacers 7 , slide onto the piston head and rod assembly. 4 Carefully inspect the bore of the cylinder and the piston rod outer diameter for scoring, nicks and burrs. If such damage is visible the components must be renewed.
6 Apply JCB Activator to threads of the end caps and cylinder. Allow Activator to dry for 15 minutes before bringing into contact with the JCB Threadlocker and Sealer (High Strength). Note 3: If burrs are evident on the ends of the piston rod at positions C or D remove by careful filing. Note 4: Neither the JCB Threadlocker and Sealer (High Strength) nor Activator must be allowed to contact seals, bearing rings or ‘O’ rings. 5 Remove the end cap seal 4 , wiper seal 5 and ‘O’ ring 6 , both end caps are the same 7 Apply JCB Threadlocker and Sealer (High Strength) to threads of the ends caps, fit new ‘O’ rings 6 . 6 Remove spacers 7 and ‘O’ rings 8 .
8 Ensure that there are no burrs at the ends of the piston rod, see Dismantling - Note 3: 9 Fit an end cap over the piston rod. Apply light hand pressure to the cap to engage the gland seal on the piston rod. DO NOT use excessive force. Screw on the first end cap and then fix the assembly on the strip/rebuild bench as shown at A . Fit the remaining cap and then torque tighten both caps. Note 5: If hydraulic oil contacts the uncured JCB Threadlocker and Sealer (High Strength) a weakening of the bond will result. Cure times vary according to the ambient temperature. Allow a minimum of 2 hours between assembly and filling the ram with oil.
Torque Settings Item Nm kgf m lbf ft 1 400 40.8 295 9803/3280 Purchased from www.WorkshopManuals.co.uk Issue 1 Section E Hydraulics Section E 88 - 2 88 - 2 Hydraulic Rams