OPERATION TRANSPORTATION I I Before lifting the machine, place the machine on a flat hori- zontal surface and follow the procedure shown below. 1. Set the machine to the position shown in the figure on the right by fully extending all cylinders (Boom at its highest point, arm and bucket fully retracted). Direct the top revolving super-structure straight forward (idler side) 2. Set the safety lock lever in the lock position. 3. Switch the engine off and confirm any loose objects are placed in the storage compartment behind the operator’s seat. Get off the machine, make sure the cab door, windshield all doors and engine hood is closed and securely locked. 4.
Mount a shackles the the lifting hooks on the boom and the counter weight. Hang the wire rope. 5. The length of the wire rope and the lifting angle must be as shown in the figure at the right. 6. When lifting, make sure that there is no change in position due to posible leakage in the hydraulic circuit on the boom cylinder head side. 1.1 m 01 or more 7. When the machine leaves the ground, stop the machine and make sure sufficiently that the machine is balanced, then lift the machine slowly. 137