Doosan DL06 — Doosan DL06 User Manual

4. Commissioning and Operation 4.1. Preparations At the time of initial commissioning of a new or overhauled engine make sure to have observed the "Technical information for the installation DOOSAN engines. z Oil filler neck on cylinder head cover Before daily starting of the engine, check the fuel, coolant and oil level, replenish if necessary. z The oil level must be between Max. and Min. lines on the gauge. The notches in the oil level gauge indicate the highest and lowest permissible oil levels. IMPORTANT: Do not fill above the top of the mark by over lifting. Over lifting will result in damage to the engine .

z Cleanliness Ensure outmost cleanliness when handling fuels, lubricants and coolants, be careful about mixing of the foreign matter during the supplement. z In case that DOOSAN recommended the fuel and lubrication oil and coolant do not used, DOOSAN do not guarantee the field claim. 4.2. Breaking-In z DOOSAN engine for the vehicle is operated during a short time for the engine last approving test, therefore operator must execute the process of proper breaking in the engine during the first 5,000 km(50 Hr), then The maximum performance of the engine have the maximum performance , and the life of the engine can be prolonged. 4.2.1.

Operation of a new engine (Break-in) Because the sliding surfaces of a new engine are not lapped enough, the oil film can be destroyed easily by overload or overspeed and the engine life-time may be shortened. Therefore the following things must be obeyed by all means. DL06 Diesel Engine Commissioning and Operation 156