Komatsu — PROCEDURE WHEN DOWNLOADING

. ATTACHMENTS, OPTIONS HANDLING PAYLOAD METER HM ATTACHMENTS, OPTIONS HANDLING PAYLOAD METER HM [Unit Setting] on screen [G2200]. Screen [G2210] is displayed. 6 - 34 4. Click [User 's Comment] i s not use d, so do not click it 5. With screen [G2210 ], it is po ssible to sele ct the communication s port (com1, c om2), specify the destination for savin g the d ownloa d data, sp ecify the file name , and select the unit to use for the data. Even if all the files are not n eeded, always select al l the files Once a setti ng has been ma de, there is n o nee d to set it again when carrying out the next download. Click [ENTE R] to re turn to sc reen [G2200 6.

On sc reen [ G2200] , click [BA CK] to r etur n to sc reen [G2000]. 7. Click [Download] on scree n [G2000]. Scree G2100] displayed, s o click [ START] t o download. After completingthe downloa doperation, c lick th e [X] at the t op right of the s creen t o close th e screen .