hitachi — Explanation of functions and operations

1J-2 Intake system (6WG1 (Common rail)) Turbocharging system Service Precautions When removing or installing the turbocharger, seal the turbine housing, compressor housing, and oil supply intake and outlet to prevent dust particles getting inside. When replacing the turbocharger and after installing the new turbocharger, inject 3~5cc of engine oil before installing the oil pipe. The turbocharger has been completed to a very precise specification (approx. 100,000rpm) and therefore cannot be disassembled. If a fault is discovered, the turbocharger ASM must be replaced. Explanation of functions and operations Turbocharger structural drawing Legend 1. Compressor cover 2. Shaft 3.

Turbine housing 4. Turbine wheel 5. Compressor wheel