Isuzu — Isuzu N Series Training Manual

1 5-8840-2245-0 2 3 4 N7A0411E N7A0409E 2. Assemble the spring (2), washer (3), shift internal lever (4), spring sheet (5), spring (6) and stopper ring (7) to the control box. Insert the shift lever shaft (1). Align the pin hole of the shift lever shaft with the pin hole of the stopper ring, and then drive in a new spring pin; stopper ring (8) and spring pin; shift le- ver shaft (9). 4. Install the detent (2). The detent contains pre-coating agent. Re- move completely the seal agent on the screw of the case side before using new detent. Tighten: Detent (2) to 28 N m (2.9 kg m / 21 lb ft) 5. Fix the neutral switch (1) to the specified torque. Tighten:

Neutral switch (1) to 34 N m (3.5 kg m / 25 lb ft) 1 1 9 2 3 4 5 6 7 8 2 N7A0410E 3. Insert the select external lever (1) and washer (2) into the control box. Install the select internal lever (3), and then drive in a new spring pin; select inter- nal lever (4). N7A0407E