Case IH AFX8010 — STORING AND HANDLING Grain storing

CROP PROCESSING - STORING AND HANDLING Grain storing 10. Close the grain elevator chain with coupler links (1) . Install “S” pins (2) to secure the coupler links. 10031281A5 8 11. Adjust the elevator chain tension with nuts (1) & (2) . NOTE: The tension is correct when the chain can be moved axially across the lower sprocket by hand when at its tightest spot. 10031282A5 9 12. Install and adjust the grain elevator intermediate shaft drive belt with nuts (1) so that spring is compressed to 56 mm ( 2.2 in ) length as indicated by guide (2) . 13. Install bearing cap (1) with nuts (2) . Close the bottom of the grain elevator with the cover (3) .

20034728B5 10 40033209E5 11 9716 1 27/05/2004 K.60.B / 22