Ditch Witch / Charles Machine Works RT40 — Trencher

RT40 Operator’s Manual Service - 139 As Needed p To install chain: 1. Lay chain on ground with teeth down and pointed toward unit. Loop cable through end links. 2. Fasten and adjust seatbelt. 3. Start tractor. See page 58 for start-up procedures. 4. Disenage parking brake. 5. Move ground drive control to reverse. 6. Back unit up until chain extends past head shaft about 1’ (305 mm). 7. Move ground drive control to neutral. 8. Lower backfill blade to ground. 9. Lower boom to horizontal position. 10. Engage parking brake. 11. Turn ignition switch to STOP. 12. Pull rear end of chain over tail roller or sprocket. 13. Pull until chain is in place on boom. 14.

Move chain down boom until chain connector pin and lock key can be installed. Install connector pin and lock key. 15. Tighten chain by pumping EPG into grease cylinder. Time Augers Ensure that augers are balanced, as shown. If auger timing is off, unit will bounce from side to side even in normal digging conditions. To adjust timing: 1. Remove bolts holding augers to auger shaft and rotate either auger as needed until augers are balanced. 2. Reinstall bolts and tighten securely. t12om081h.eps