Komatsu — 930E CHASSIS ASSEMBLY PROCEDURE

16. If installed (some trucks are shipped with the center deck not installed), the center deck should be removed to enable easy installation of air intake tubing and the two diagonal cross tubes. Refer to Figure 6-23. The weight of the center deck is approximately 550 lbs. (249 kg) . 17. Lift the LH diagonal tube into position (Figure 6-25). The weight of the LH diagonal tube is approximately 344 lbs. (156 kg) . Loosely install the capscrews until the deck and cab is in place. After installation of the deck and cab, tighten the sixteen capscrews (M24) to 590 ± 59 ft.lbs. (800 ± 80 N.m) torque. Page 6-28 930 FIELD ASSEMBLY MANUAL FAM0607 Chassis Assembly