OPERATIONAL PERFORMANCE TEST / Component Test Pilot Characteristics Summary: Main pump performance is checked by measuring the pump flow rate by using a hydraulic tester installed at the main pump delivery port to be measured. Use Dr. ZX and a pressure gauge at the same time. IMPORTANT: This measurement procedure is a simple method. The measured data will be lower by approx. 5 % than the accurately measured value. In order to measure accurately, disconnect the return circuit from the control valve and connect it to the hydraulic oil tank. 7. Remove the vacuum pump. Loosen the plug on top of the pump casing. Bleed air from the pump casing until oil only comes out of the plug clearance. 8.
Fully open the loading valve of the hydraulic tester. 9. Start the engine. Check for any oil leaks at the pipe connection. Measurement: 1. Maintain the hydraulic oil temperature at 50 ± 5 ° C (122 ± 41 ° F) 2. The pump flow rate in response to the external command pilot pressure is measured. 3. Set engine speed at fast idle. Depress the accelerator pedal fully 4. Adjust the pressure reducing valve set pressure to each pressure point specified along the main pump P-Q curve. (Pilot Characteristics) (Refer to T4-2.) Measure the flow rates and engine speeds at the pressure points specified in the P-Q curve. 5. Repeat the measurement three times and calculate the average values. Evaluation: 1.
Convert the measured flow rates to those at the specified pump speed by using the following formulas: Qc = (Ns Ч Q) / Ne Qc : Converted Flow Rate Q : Measured Flow Rate Ns : Specified Engine Speed : ZW220: 2170 min -1 ZW250: 2240 min -1 Ne : Measured Engine Speed Value by Dr. ZX 2. Standard Flow Rate Refer to the Performance Standard Table in Group T4-2. Preparation: 1. Refer to steps 1 to 4 on page T4-5-16. Install a hydraulic tester to the main pump. 2. Remove the hose from regulator port Pi1 of the pump. Install a plug to the removed hose. : 19 mm 3. Install adapters (13) (3 used) to pressure reducing valve (14). Remove the hose from port P of the orbit roll.
Insert tee (10), adapter (11) and hose (12) between orbit roll and charging block. Install hose (12) to port P1 on reducing valve (14). : 19 mm 4. Install tee (15) to port P2 on pressure reducing valve (14). Install pressure gauge (16) and hose (12) to tee (15). Install hose (12) to regulator port Pi1. : 19 mm 5. Install hose (12) and adapter (13) to port T on pressure reducing valve (14). Remove plug L from the return pipe. Install hose (12). : 19 mm 6. Connect regulator port Pi2 to the hydraulic oil tank. As for the emergency steering, install tee (17), adapter (18) and hose (19) to port E in the emergency steering block. Install hose (19) to regulator port Pi2. T4-5-18