Freightliner — Freightliner Business Class M2 Workshop Manual

Trailer Electrical Systems 54.29 PDM Removal and Installation 1 2 3 4 5 3 4 5 04/23/2002 f544104 2 1. Left Frame Rail 2. PLC Filter 3. Trailer PDM 4. #10 Washer 5. 10-24 Nut Fig. 2, Trailer PDM Aft-of-Cab Installation 11/10/2005 f544692 1 3. Using a nut and washer, install the positive lead on the trailer PDM battery power stud. Torque the nut 11 to 13 lbf·ft (15 to 18 N·m). 1. Trailer PDM 2. Mounting Bracket 3. Crossmember 4. #10 Washer 5. 10-24 Nut 4. Using capscrews, attach the metal cover (that protects the PDM) to the mounting plate. Fig. 3, Trailer PDM End-of-Frame Installation 5. Connect the batteries or turn the battery discon- nect switch to on. 6.

Verify the operation of the trailer electrical com- ponents. 7. Remove the chocks from the tires. Business Class M2 Workshop Manual, Supplement 10, September 2006 100/2