Hitachi Construction Machinery — Valve Clearance

OPERATIONAL PERFORMANCE TEST / Engine Test VALVE CLEARANCE Summary: 1. Perform the measurement when the engine is cold. 2. Before starting any work, clean the head cover mounting area and avoid contamination in the engine. Preparation : 1. Remove the head cover. 2. Remove the terminal nut which secures the har- ness to the injector. Harness Terminal Nut : 2 N m (0.2 kgf m, 1.5 lbf ft) 3. Remove the bolts (2 used). Remove the harness assembly from the injector. T1J1-04-03-006 Injector : 22 N m (2.2 kgf m, 16 lbf ft) 4. Remove the leak off pipe. Bolt: Bolt : 15 N m (1.5 kgf m, 11 lbf ft) 5. Rotate the crank pulley.

Align the T/C mark on flywheel with the pointer on gear case in order to get TDC in the compression stroke. NOTE: When rotating the crank pulley, remove the fan guard. Then, rotate the fan while hold- ing the fan belt. If it is difficult to rotate, re- move all glow plugs and release compres- sion pressure. 6. Check if piston No.1 (or piston No.6) is now posi- tioned at the T/C in the compression stroke. Harness Assembly T1J1-04-03-007 Leak Off Pipe NOTE: Move push rods for the intake and exhaust valves on the No.1 cylinder up and down by hand. If any clearances on the both ends of the push rods are found, piston No.1 is positioned at T/C in the compres- sion stroke.

(If the exhaust valve of cylinder No.1 is pushed down, piston No.6 is posi- tioned at T/C in the compression stroke. 7. Start measurement from the cylinder (No.1 or No.6) positioned at T/C in the compression stroke. T1J1-04-03-008 T/C Mark Pointer Gear Case Flywheel T1J1-04-03-003 T4-3-4