Hitachi Construction Machinery — Boom Raise/Swing Combined Operation Check

OPERATIONAL PERFORMANCE TEST / Excavator Test BOOM RAISE/SWING COMBINED OP- ERATION CHECK Summary: Check boom raise and swing movement speeds while operating both functions simultaneously. Preparation: 1. Start the engine and run it at fast idle. Operate the boom raise function and check to be sure that the cylinder movement is smooth, with out sticking. 2. Position the machine with front attachment posi- tioned as illustrated and with the bucket empty. 3. Maintain the hydraulic oil temperature at 50 ± 5 ° C (122 ± 41 ° F). M104-07-021 CAUTION: Prevent personal injury. Always make sure that the area is clear and that co- workers are out of the swing area before starting the measurement.

Measurement: 1. Measurement conditions are as below. T107-06-03-010 2. Raise the boom and swing simultaneously. 3. When the upperstructure rotates 90 ° , release the control levers to stop both functions. Measure the time required to swing 90 ° and the height (H) of the bucket teeth. 4. Perform the measurement three times and cal- culate the average values. Evaluation: Refer to the Operational Performance Standard in Group T4-2. Remedy: Refer to the Troubleshooting B in Group T5-7. H T107-06-03-011 T4-4-17 Engine Control Dial Power Mode Switch Work Mode Auto-Idle Switch Fast Idle HP Mode Digging Mode OFF