Kaiyi D375A-6 — A-12 Installation of blade

98 Assembly process No. Installation of blade (7/9) A-12 6.4) After aligning the pin holes, stop the engine and insert pin (12) removed in step 6.1) and fix it to Fig. 13 the blade with lock (13), bolt (14) and washer (15). (Fig. 13) a Perform the work from step 6.2) to step 6.4) on the right and left sides. However, perform on only the right side for the single tiltdozer. a For the tightening torque of bolt (14), see "Tight- ening torque", Table 1 in this manual. 6.5) Loosen and remove the slings of the hydraulic cylinder. 6.6) Start the engine again and operate the blade control lever to raise the whole blade assembly. Then, remove all the wooden blocks placed under the blade.

6.7) Lower the blade to the ground and stop the engine. 7) Confirmation of operation of blade assembly 7.1) Check of hydraulic oil level and supply of new oil [1] Check the hydraulic oil level again and supply new oil, if necessary. a Confirm the oil level after lowering the ripper shank and blade to the ground and set the back of the blade perpendicular to the ground. a About the kind of used fluids refer to “Assembly procedure A-20” Check on the amount of lubri- cants and coolant. a If the hydraulic oil level is low, the work equipment pump may be damaged.

7.2) Check of each part for interference [1] Move the blade slowly and check that each part does not make interference or abnormal sound. If abnormal sounds seem to come from the ball joints at both ends of the center brace, see step 7.5). [2] Confirm that the blade does not interfere with the machine (radiator guard) when it is tilted to the maximum (or dual-tilted to the maximum for the dual tiltdozer) at the maximum lifting height. [3] Confirm that there is sufficient clearances between the straight frames of the blade assembly and the tracks of the undercarriage when the blade is tilted to the maximum (or dual-tilted to the maximum for the dual tiltdozer). Fig. 13 Fig. 13 Fig. 13