Kaiyi D375A-6 — A-10 Installation of track

74 Assembly process No. Installation of track (1/2) A-10 Note) This work is required for disassembly to 32-t parts for transportation. 1. Installation of track link Fig. 1 1-1) Wind the front end of each track up to the top of the idler. (Fig. 1) 1-2) While rotating the sprockets forward, dis- charge the grease from the cylinder and retract the cylinder to the stroke end. a Keep the grease plug open. a Clean the master link joint. T 300 mm × high 600 mm 1-3) Push up the machine with the ripper and dis- engage the link from the sprocket so that the Fig. 2 machine body will not run on the track. (Fig. Wire 24 ø × 2 m 2) a Put a steel plate on the block to protect the block.

Inserted Steel plate 25 mm thick T 300 mm × high 600 mm Floated a Carry out this work on a level place. Fig. 3 1-4) Sling the forward end of the track with a crane and wind the track link up to the top of the sprocket as shown in the photo. (Fig. 3) 1-5) Wind the track onto the sprocket. While slinging the forward end of the track with the crane, rotate the sprocket to move only the upper part of the track forward. a The signal person must stand at a posi- tion where the bulldozer operator and crane operator can see him/her easily and must give signals. Before starting the work, confirm the signals. Fig. 4 1-6) Connect the master link just above the idler.

1-7) Fit the mating faces of the master link and check that you can screw in the bolts lightly. (Fig. 4)