Komatsu — WORK EQUIPMENT - TWO PIECE BOOM

MAINTENANCE STANDARD WORK EQUIPMENT - ONE PIECE BOOM .

o N y d e m e R 1 2 3 e c alp e R 4 5 6 40-32 40-31 Checkitem Criteria Clearancebetween connectingpinand bushingofrevolving frameandboom Standard size Tolerance Standard clearance Clearance limit Shaft Hole 70 -0.030 -0.100 +0.140 +0.074 0.104- 0.240 0.8 Clearancebetween connectingpinand bushingofboomand arm 70 -0.030 -0.100 +0.141 +0.074 0.104- 0.241 0.8 Clearancebetween connectingpinand bushingofarmand link 60 -0.030 -0.080 +0.130 +0.074 0.104- 0.210 0.8 Clearancebetween connectingpinand bushingofarmand bucket 60 -0.030 -0.080 +0.129 +0.074 0.104- 0.209 0.8 Clearancebetween connectingpinand bushingoflinkand bucket 60 -0.030 -0.080 +0.135 +0.074 0.104- 0.215 0.8 Clearancebetween connectingpinand bushingoflinkand link 60 -0.030 -0.080 +0.133 +0.074 0.104- 0.213 0.8