daewoo Solar 140LC-V — Shimming Procedures for Installed Bucket

BUCKET SHIMMING PROCEDURES NEW BUCKET INSTALLATION 1. If a new bucket is being installed on the excavator, measure the inside dimension between the bucket ears and the outside dimension across the arm mounting boss. 2. Subtract the clearance on both sides from the difference of the two and shim accordingly, before assembly. WARNING! To check end play (side-to-side) clearance at bucket attachment point, the bucket must be free to move but at all other times lower it to the ground or use support blocks to immobilize this assembly. Shut off engine and tag and lock out controls to prevent movement during this procedure. SHIMMING PROCEDURES FOR INSTALLED BUCKET 1.

With bucket attached, curl bucket and arm outward and lower boom so that bucket teeth are pointing away from excavator, just a few inches off ground. This position provides easy accessibility for dimensional measurements. 2. Force bucket to one side and check for end play (side-to-side) clearance under O-rings at attachment point. Total clearance should be 1 mm (0.04 in) between side face of boss and inside edge of ear bushing (Y, Figure 87). Too tight a fit (less than 1 mm (0.04 in)) can cause excessive wear while too much clearance may produce excessive noise and potentially hazardous slack control. "X" "Y" 1 3.

Recheck end play by forcing bucket towards opposite side and repeating clearance measurements. 3 4 2 4. If an adjustment is required, remove two jam nuts (1, Figure 87) and bolt (2) from pin (3). Add or remove shims (4) as required. Use equal amount of shims on each side. Install bolt (2) and two jam nuts (1). Jam nuts must clear boss by 1 - 2 mm (0.04 - 0.08 in) at point (X). BBO0040L Figure 87 022-00058E Operation and Maintenance Manual Inspection, Maintenance and Adjustment 4-57