© 0988 Injection Pump Removal / Refitment Job Card No.: 07.04.01 Page 1 of 8 Engine: S/BV 6/8/9 M 628 Filing No.: 0178-18-10 2059 The described job sequence must be strictly Tools: adhered to and followed for each removal and - Standard tools refitment of injection pump. - Feeler - Gauge If an injection pump has to be disassembled for repair - Hoist purposes it has to be brought to a DEUTZ- Service - Torque wrench (Section 1.8) station and calibrated there - following its reassembly - 2 Dial gauges (Section 1.8.1) - to the same injection quantity and set to maximum fuel stop power. The accessory carrier with attach- Job Cards:
ments will be removed and refitted together with the - 02.00.01 injection pump. - 05.04.01 - 05.04.14 Job: - 07.01.01 Before removing the injection pumps - 07.03.01 - 07.03.02 G Observe safety regulations as per job card - 07.06.01 02.00.01. G Put all injection pump tappets out of operation by actuating the lifting devices (see job 07.01.01). G Remove cover from pump drive. G Remove all fuel and lube oil pipes. G Remove injection lines (job 07.03.01). G Remove governing linkage (job 05.04.14) as necessary. G Remove hydraulic speed governor (job 05.04.01). or G Remove electronic governor, undo cable connections. G Remove lube oil pump for valve seat lubrication (job 07.06.01).
G Remove respective timing cover. G Mark with scriber (18) position of injection pump drive gear (8) - Fig. 1 - relative to shaft section (19). G Mark (11) position of shaft section (19) relative to shaft (14). G Loosen bolts (1) and (8) - Fig. 2. G Loosen cheese head fastening bolts (17) - Fig. 1 - of drive gear until the injection pump drive shaft (14) can be turned by hand. The clamping connection must be unclamped but there must be no gap between the two shaft sections (19) and (15), i.e. they should have no play. © 50 287 1 Fig. 1 © 50 287 1 © 50 287 1