Front Axle - Wheel, Rim and Tyre Section 140-0040 hot enough. Slide heated bushing (14) on spindle (8) and tap lightly with a hammer to seat it. only two bolts (2) located 180 o apart, adjacent to the gauging holes in plate (3). Tighten bolts (2) evenly in equal increments to 'Gauging Bolt Torque', as specified in 'Bearing Adjustment Table', while rotating and bumping wheel (7) assembly. Note: Do not apply flame directly to bushing. Place bushing on steel plate and apply flame to centre of plate, to evenly distribute heat. 11. Determine gap between plate (3) and end of spindle (8) at both gauging holes.
To determine gap, use a depth micrometer in both gauging holes to measure distance from outer face of plate (3) to end of spindle (8). Using a micrometer, measure thickness of plate (3). Subtract plate thickness reading from depth gauge readings. 2. If removed, install bearing cups (6 & 10) in their respective wheel (7) bearing bores with care to avoid damaging their raceways. Installation by press fit at ambient temperature is best. Note that the cups must seat fully against the shoulders of the cup bores in the wheel hub to assure retention of bearing adjustment.
If carbon dioxide, or dry ice, freezing of the cup is used, remember to permit the cup and hub to warm to ambient temperature after insertion and then to tap them with a soft steel drift and hammer to seat. 12. Average the two readings, obtained at Step 11, in increments of 0.025 mm (0.001 in) and round off to the next higher 0.025 mm (0.001 in). This is the average gap. The required shim pack (4) thickness is equal to the average gap plus the tabulated constant as shown in the 'Bearing Adjustment Table'. 3. Lubricate the bearings with lubricant specified in Section 300-0020, LUBRICATION SYSTEM. Do not pack bearings solidly with lubricant, as too much is harmful.
Fill wheel cavity not less than one-third to not more than one-half full with lubricant. 13. Install the required shim pack (4), plate (3) and bolts (2) on the end of spindle (8). Tighten bolts (2) evenly in equal increments to 'Final Bolt Torque', as specified in 'Bearing Adjustment Table', while rotating and bumping the wheel (7) assembly. Secure bolts (2) with lockwire (1). 4. If removed, install brake disc (17) on wheel (7) and secure with bolts (15) and lockwashers (16). Tighten bolts (15) to a torque of 420 Nm (310 lbf ft). 14. Install gasket (21) and cover (20) and secure to wheel (7) with bolts (18) and lockwashers (19). 5.
Install inner cone (9), washer (11), snap ring (12) and seal (13) in wheel end facing spindle. Seal lip must be facing out. 15. Install brake calliper, connect brake hydraulic line and bleed braking system. Refer to Section 165-0020, BRAKE PARTS. 6. With suitable lifting equipment slide wheel (7) assembly onto spindle (8). 7. Install outer bearing cone (5) on spindle (8) and seat in outer bearing cup (6). 16. Install tyre and rim assembly as described under 'Mounting Tyre and Rim Assembly on Machine'. Note: Ensure all dirt, grease, and oil is completely removed from plate (3), shims (4) and end of spindle (8) to allow accurate setting of the bearing pre-load. TYRE INFLATION 8.
Install plate (3), without shims (4) on end of spindle (8), and secure with six bolts (2). Tighten bolts (2) evenly in equal increments to 'initial seating bolt torque' as specified in 'Bearing Adjustment Table', while rotating and bumping the wheel (7) assembly. WARNINGS To prevent personal injury and property damage, the tyre and rim assembly should be placed in a safety cage before inflating. If no safety cage is available or tyre is on the machine, the tyre and rim assembly should be wrapped with safety chains or with lash cables before inflating. 9. Remove bolts (2) and tap wheel (7) assembly to free bearings. Even with these precautions remember that air-blast is a potential hazard.
Tyre inflation should be carried out away from busy working areas. 10. Reassemble plate (3) without shims (4) and using SM 1579 12-98 7