Downloaded from https://www.everyspec.com MIL-HDBK-502: A MIL-HDBK-502: A CQUISITION CQUISITION L OGISTICS OGISTICS Section 8: Logistic Considerations for Contracts 8.1 INTRODUCTION AND OVERVIEW OF UNIFORM CONTRACT FORMAT Experience has shown us that properly prepared solicitations and contracts are key ingredients in the success of acquisition programs. Logistics considerations are a major consideration during research and development and during the acquisition process. They are, therefore, a large part of the solicitation and ultimately the contract.

All personnel responsible for designing, developing, and acquiring systems must work together to ensure that logistics needs are adequately covered in contractual documents. The term, “solicitation,” refers to the document that is used by the government to communicate its requirements to prospective contractors, to solicit proposals or quotations, or to unilaterally order or modify a contract. The Uniform Contract Format (UCF), outlined in Figure 8-1 below, is the format used in typical acquisition contracts to structure a solicitation, including logistics support for weapon systems.

Support systems managers (SSMs), logistic elements managers (LEMs), and integrated product team (IPT) members must be thoroughly familiar with this format, and understand how the solicitation and its procedures assist them in completing the relevant sections of the UCF. SSMs, LEMs, and IPT members are involved in preparing Sections B, C, D, E, F, H, J, and L of the UCF when contracting for logistics efforts.

8.2 SYSTEM ACQUISITION Solicitations are normally developed and issued at the beginning of each phase of the acquisition life cycle (Concept Exploration, Program Definition and Risk Reduction, Engineering and Manufacturing Development, and Production, Fielding/Deployment and Operational Support). These solicitations and the contracts that follow them are usually based on: the results of the previous phase, the present state of program development, and the acquisition strategy. 8-1