Downloaded from https://www.everyspec.com MIL-HDBK-502: A MIL-HDBK-502: A CQUISITION CQUISITION L OGISTICS OGISTICS Quantifiable and testable requirements This topic is addressed in more detail in Section 6. An important responsibility of the logistician on an IPT is to help the team create supportability performance requirements that are quantifiable and testable so that the decision-makers can gain insight into the operational suitability of the product and the logistics planners can plan for the support of the item. Accepting trade-offs This is an extension of the “Reasoned Disagreement” principle covered previously.
Not only must IPT members provide alternative solutions if they disagree with a plan of action, but they must also accept the fact that in any program compromises must be made, and their alternative may not be accepted. This is particularly true in the logistician’s case because the implications of his or her disagreements often have large and far-reaching effects on the overall program. Often the issue raised by the logistician falls into the category of deciding to accept significant upfront costs to avoid even more significant future costs. 9.3 SUPPORTABILITY IPTS 9.3.1 Who to Invite Of course no standard recipe exists for who should be on a supportability IPT.
Membership should be based on the particular needs of the program, the type of IPT (program or working-level), and the desires of the leadership. However, some general rules apply. First, the membership should be made up of representatives from those organizations or functional disciplines that will influence the product throughout its lifetime. A second, closely related approach is to include on the team a representative from every organization that can stand in the way of the program’s advancement. Using this approach keeps the other team members from having to play devil’s advocate themselves and ensures that problems will be reviewed early in the process.
The temptation is to do the opposite and exclude those people, but in the long run inclusion is better. In general a supportability IPT should be comprised of: the customer or user prime contractor and key suppliers or vendors manufacturing design support management 9-7