omron — 5.2. Work Flow

Work Flow 5.2. Take the following steps to make the tag data link connection settings for EtherNet/IP. 5.3 Setting up the RFID System Set up the RFID System. ↓ 5.3.1 Parameter Setting Set the parameters of the RFID System. ↓ Set up the Controller. ↓ 5.4.1 Starting the RSLogix5000 and Start the RSLogix Software, and configure the controller. Configuring the Controller ↓ Set the tag data links for the EtherNet/IP. ↓ 5.5.1 Configure RFID within the Configure RFID to communicate over the network. Network ↓ 5.5.2 Going Online and Transferring Going Online and Transferring Tag Data Link Parameters to the Controller.

Tag Data Link Parameters ↓ Confirm that the EtherNet/IP communications are performed normally. ↓ 5.6.1 Checking the Connection Status Check the connection status of EtherNet/IP. ↓ 5.6.2 Checking Data that are Sent and Confirm that the correct data are sent and received. Received 8 5.4 Setting up the Controller 5.5 Setting up the Network 5.6 Checking the EtherNet/IP Communications