Department of Defense MIL-STD-705C — MIL-STD-705C Generator Sets Engine-Driven Test Methods Standard PDF

Downloaded from https://www.everyspec.com MIL-STD-705C METHOD 695.1a RELIABILITY TEST 695.1.1 General. The reliability test is designed to measure the probability that a generator set will perform as intended. While this test method is called “Reliability Test”, the actual parameter developed will be the Mean-Time-Between Failure (MTBF). This method may be used for a time-terminated reliability test or a probability ratio sequential reliability test as required by the procurement document. 695.1.2 Apparatus. Instrumentation for measuring load conditions and ambient temperatures shall be as described and illustrated in MIL-HDBK-705.

In addition, recording meters as described and illustrated in MIL-HDBK-705, methods 101.1 and 104.1 (unless otherwise specifid in the procurement document) for recording voltage and frequency, and an elapsed-time meter will be required. 695.1.3 Procedure. 695.1.3.1 Preparation of test. a. Unless otherwise specified in the procur ement document, the generator set shall be placed outdoors such that it is completely exposed to the weather on all sides, and shall be placed directly on a level, solid reinforced concrete surface at least 3 inches thick and having a total weight at least equal to the weight (wet) of the generator set. The generator set should not be restrained in any manner.

If the generator set must be restrained to prevent “walking”, the test results shall so indicate. b. Connect the load instrumentation in accordance with the applicable figure of MIL-HDBK-705, method 205.1, paragraph 205.1.10, for the voltage and frequency condition specified in the procurement document. Unless otherwise specified, connect the signal input of the recording meter(s) to the convenience receptacle of the set or to the generator coil which is used as the voltage-sensing input to the voltage regulator.

For generator sets having more than one power output system (e.g., high voltage ac and low voltage dc, set battery charging system not included, or two ac systems or different frequencies), separate loads and instrumentation are required for each system. The elapsed-time meter for monitoring set operating hours shall be relay operated for commercial power with the relay coil being energized from the set convenience receptacle or the generator side of the coil of the circuit interrupter. 695.1.3.2 Failure definition. The contracting officer shall have final determination of all failure classifications.

The failure definition below shall be used unless otherwise specified in the procurement document: a. A reliability-chargeable failure shall be defined as an event other than scheduled maintenance in which malfunction occurs, resulting in the replacement of the malfunctioning item (part, component, subassembly, or assembly) by a like item, except as provided in the servicing and Method 695.1a 1