beckhoff TS1110 — 7 First steps

First steps 7 First steps Prerequisites: The Original (to be simulated) PLCs projects are ready and the system manager configuration has been created and is activated on the target. The PLC projects used should contain the TcSimMan.lib for simulation purposes. At minimum one PLC must be free on the local system (local simulation) or on a remote system (distributed simulation). All used target systems (local or remote) must have a valid configuration activated. The PLC runtimes must contain the Symbol description files PLC runtimes must be configured as boot project see also Requirements for Simulation configurations [ } 17] .

Creation of new TwinCAT Simulation Manager project Select "File --> New" in the main menu (see Picture 1 [ } 67] ) Fig. 52: Picture 1: Open a new project An "Open new Project" dialog appears and a valid Project name and Location path must be inserted. Press "OK" (see Picture 2 [ } 67] ). TS1110 67 Version: 1.0