Veeder-Root — TEST REPORT FORM TEMPLATE - ENA Eng

Page 18 of 190 Report No.: 6068396.50 TRF No. G99/1-4_V1.0 G99/1 Clause Requirement - Test Result - Remark Verdict 9.1.4 Power Generating Modules should meet a set of technical requirements in relation to its performance with respect to frequency and voltage, control capabilities, protection coordination requirements, Phase (Voltage) Unbalance requirements, neutral earthing provisions, islanding and Black Start Capability as applicable. The technical connection requirements in this chapter are common to all Power Generating Modules. P 9.1.5 In addition requirements for Type A Power Generating Modules are detailed in Section 11.

Requirements for Type B Power Generating Modules are detailed in Section 12. Requirements for Type C and Type D Power Generating Modules are detailed in Section 13. P 9.2 Network Connection Design for Power Generating Modules P 9.3 Step Voltage Change and Rapid Voltage Change P 9.4 Power Quality See appended table. P 9.4.1 Introduction P 9.4.1.1 The connection and operation of Power Generating Modules may cause Phase (Voltage) Unbalance and/or a distortion of the Distribution Network voltage waveform resulting in voltage fluctuations and harmonics.

P 9.4.2 Flicker P 9.4.2.1 Where the input motive power of the Power Generating Module may vary rapidly, causing corresponding changes in the output power, flicker may result. The operation of a Power Generating Module including synchronisation, run- up and desynchronisation shall not result in flicker that breaches the limits for flicker that is non-compliant with EREC P28. P 9.4.2.2 The supply impedance of the Distribution Network needs to be considered to ensure that the emissions produced by the Power Generating Module do not cause a problem on the Distribution Network.

P 9.4.2.3 For Power Generating Modules up to 17 kW per phase or 50 kW three phase voltage step change and flicker measurements as required by BS EN 61000-3-11 shall be made and recorded in the test declaration form A2-1 or form A2-3 as applicable for the Power Generating Module. The DNO will use these declared figures to calculate the required maximum supply impedance required for the connection to comply with EREC P28. This calculation may show that the voltage fluctuations will be greater than those permitted and hence reinforcement of the Distribution Network may be required before the Power Generating Module can be connected. Detailed testing requirements are described in Annex A.7. P