Downloaded from https://www.everyspec.com AMCP 706-1N Examp~le No. 25 Compare the "average clook-time for a test that requires that all 10 units (10 test stations) fail" with the "average clock-time for a test In which 10 units of 20 fail (20 test stations)." r Example i. State the values of r and a, 1. r 10, s 20. 2. Determine the ratio of E{I,.,D} to 2. From Table 3-7, ratio 0. 23. * E*vP from Table 3-7. This result clearly indicates the substantial savtngs in clock-time (on the average) which can result from using more than the minimum number of test stations (in the nonreplacement case). ;i 'I ....