Komatsu — E-16: INSTALLATION OF BOTTOM DUMP CYLINDER PIPING

E-l 6: INSTALLATION OF BOTTOM DUMP CYLINDER PIPING [A] When the bucket assembly is installed to the arm as shown in the diagram on the right. (1) Install the bottom dump cylinder (07099- 21214 x 2) short circuited for flushing in their original positions. the hose mount with new parts. Replace the O-rings (%07000-13038 x 3) at (2) Install the 2 removed rear bucket covers (209- 72-54271) to their original positions. [B] When the bucket assembly has been disassembled as shown in the figure on the right, use the pro- cedure given on the following pages to assemble the bucket, then install the 2 bottom dump cyl- inder hoses (~07099-21214).

hose mount with new parts in the same way as in Replace the O-rings (%07000-13038 x 4) at the [Al . Then install the 2 covers (209-72-54271). 120