Komatsu — E-23: BLEEDING AIR FROM WORK EQUIPMENT CIRCUIT

E-23: BLEEDING AIR FROM WORK EQUIPMENT CIRCUIT After completion of assembly of the work equipment piping, bleed the air from the system. arc digging. [ I Be sure to set the arc/horizontal selector switch to Arc digging symbol I I Run the engine at low idling out going to the end of its stroke (stop approx. Extend and retract each cylinder 4 or 5 times with- + At first there is a large amount of air inside the 100 mm before the end of the stroke). cylinder, so the cylinder may not move for the the lever to the end of its travel. first ten seconds.

In such cases, do not operate Keep the engine running at low idling, and operate each cylinder from a point 100 mm from the end of its stroke slowly (take at least 10 seconds) to the work equipment control lever at the full stroke end of its stroke (fully extended), and hold the position for 3 minutes. cylinders when they are fully extended, but air is (The air is bled from the boom, arm, and bucket fully retracted (bucket open).) bled from the bottom dump cylinder when it is 5.

Next, run the engine at high idling, and operate each cylinder from a point 100 mm from the end end of its stroke (fully extended), and hold the of its stroke slowly (take at least IO seconds) to the work equipment control lever at the full stroke position for 1 minute. cylinders when they are fully extended, but air is (The air is bled from the boom, arm, and bucket bled from the bottom dump cylinder when it is fully retracted (bucket open).) * inders.

Repeat Steps 3 - 5 to bleed the air from the cyl- * If this operation is carried out from the first with the engine running at high speed or with the cyl- inder operated to the end of its stroke, the air contained inside the cylinder may cause damage to the piston packing. 133