honda — Electrical Equipment

• FRAME GROUND INSTALLATION: Tighten the 6 x 12 mm flange bolts while pushing each ground terminal against the projection on the crankcase as shown. [2] FRAME GROUND TERMINAL [3] POWER TILT RELAY GROUND TERMINAL [1] PROJECTIONS • POWER TILT RELAY GROUND CABLE INSTALLATION: 1) Connect the Black, Blue, Green/White wire side of the ground terminal to the upper connection, and the Green, Green/Black, Blue, Black/White wire side of the ground terminal to the lower connection as shown. 2) Tighten the 6 x 12 mm flange bolt while pushing each frame ground terminal against the projection on the crankcase. [4] PROJECTION [5] FRAME GROUND TERMINAL b.

INSPECTION • POWER TILT RELAY Note that the power tilt relay inspection must be made on single unit of the power tilt relay. 1) Check for continuity between the terminals. [1] GROUND WIRE Bl Bu Lb Lg W G 18-29 Green to Black terminals Continuity Blue to Black terminals Continuity Green to White terminals No continuity Blue to White terminals No continuity