JCB — Flow and Pressure Testing

www.WorkshopManuals.co.uk Variable Flow Pumps Flow and Pressure Testing (Cont’d) Pump Flow Load Sense Line Flow It is not possible to test full pump flow at system pressure whilst the pump is installed on the machine. This is because the pump swashplate angle will return to minimum angle (zero flow) when the system reaches full pressure (see descriptions). The load sense line communicates the load pressure required at a service to the pump. If there is a blockage or leak in the line, the hydraulic system will not operate effectively. However, it is possible to test the pump flow whilst ‘blowing off’ an auxiliary relief valve which is set lower than system pressure.

In the example below, the shovel head side A.R.V. is used. The readings taken in this test give a ‘snapshot’ of pump performance and can be used to establish if major pump maintenance is required. Load sensing is a ‘dynamic flow’ type. That is, there is a constant flow of oil from the pump to the shuttle valves. When a pressure signal is felt at the service port, the flow is interrupted and the pump immediately responds to the demand. (Unlike a ‘static’ system where the pressure signal must move from the valve block, back up the load sense line to the pump). 1 Warm the hydraulic oil to working temperature, i.e. 50°C (122°F): 1 Warm the hydraulic oil to working temperature, i.e. 50°C (122°F):

a Set the engine speed to 2200 rev/min. a Set the engine speed to 2200 rev/min. b Operate the loader shovel dump service to blow off the auxiliary relief valve. b Operate the loader shovel dump service to blow off the auxiliary relief valve. 2 Lower the backhoe bucket and loader shovel to rest on the ground; stop the engine; operate the control levers to vent residual hydraulic pressure. 2 Lower the backhoe bucket and loader shovel to rest on the ground; stop the engine; operate the control levers to vent residual hydraulic pressure. 3 Connect a 0 - 400 bar (0 - 6000 lbf/in 2 ) pressure gauge to pressure test connector B located on the pump pressure out line.

3 Connect a flowmeter into the load sense line, a good access point is where the LS line enters the backhoe valve as shown at D . 4 Connect a flowmeter to the pump pressure out line as shown at C . 5 Start the engine and run at 2200 rev/min. Check the flow which should be as specified in Technical Data . 5 Start the engine and run at 2200 rev/min. 6 Raise the loader arms and fully dump the loader shovel. 6 If a service is selected, the flow should drop to zero (but the pressure will increase). 7 If there is no flow in the system, then check the load sense lines for being trapped or kinked, also move the service control levers and the steering wheel.

7 Hold the shovel in the dump position (to blow off the A.R.V.) and check the flow and pressure gauge readings, which should be as specified in Technical Data . If there is still no flow, then there is the possibility of a shuttle valve being stuck. Do not dismantle valves at this stage but complete all other tests listed in this section. 8 If the pump flow is not as indicated, do not make any adjustments at this stage. Complete the other checks detailed in this section. 9 Refer to Regulator Valve Adjustment . 9803/3280 Purchased from www.WorkshopManuals.co.uk Issue 1 Section E Hydraulics Section E 22 - 4 22 - 4 Service Procedures