9803/3280 Purchased from www.WorkshopManuals.co.uk Issue 1 Section E Hydraulics Section E 27 - 2 27 - 2 Service Procedures Hose Burst Protection Valves Pressure Testing - Loader Lift Ram The following text describes the pilot valve setting procedures and pressure testing sequences for ONE HBPV only, repeat the procedures for BOTH loader arm lift rams. Preparation Before starting the pressure testing procedure vent hydraulic system pressure as follows: 1 Park the machine on firm level ground, engage the parking brake and set the transmission to neutral. 2 Lower the loader arms to the ground (not lifting the machine).
3 Select 'ARMS LOWER' to raise the front wheels approximately 25 - 50 mm (1 - 2 in) off the ground. 4 Switch off the engine. 5 Make sure all personnel are clear of the machine before completing step 6. 6 Select 'ARMS RAISE' - this will vent residual hydraulic pressure from the loader rams (head side). 7 Move all the backhoe control levers back and forth to vent any other residual hydraulic pressure from the backhoe service hoses. Pilot Valve Setting Procedure The pilot valve assembly, shown at C, must be set correctly before doing the relief valve pressure test.
If the pilot valve is screwed too far into the HBPV it will create a flow path connection from port C2 to port V2 (see descriptions of operation). To set the pilot valve assembly: 1 Remove pilot housing, item D, from the HBPV. 2 Check that the end face of the pilot valve assembly, item C, is flush (level) with the end face of its housing D, as shown at E. 3 If necessary, remove end cap F and, using a suitable Allen key, adjust the pilot valve as required. 4 Refit the end cap. Continured............ K J B A G E D C F 327330