1E-202 Electronic control fuel injection system (Common rail type) About PCV Breaker box inspection procedure Perform the inspection in the following procedure if there is such an instruction to use breaker box in the step. After inspection, return to the diagnostic step. 1 2 TSWG0010 Name 1. PCV #1 2. PCV #2 Name 1. Breaker box 2. DMM Name 1. PCV-HI 2. PCV-LO Step Item to be checked Inspection method Measuring condition Terminal No. Normal value Abnormal value 2 Short circuit to power supply circuit Voltage measurement • Remove the PCV connector.
• Key switch “ON” 105 - Ground 113 - Ground 89 - Ground 97 - Ground 0V 18V or more Short circuit to other signal circuit Voltage measurement • Remove the PCV connector. • Key switch “ON” 105 - Ground 113 - Ground 89 - Ground 97 - Ground 0V 1V or more