DRESSTA Co. Ltd. 560C99/1E — 5.20. LOADER EQUIPMENT

SECTION 5 MAINTENANCE Page 52 LOADER EQUIPMENT To replace the bucket carry out as follows: 1. Park the machine on level ground or in the workshop. 2. Place the bucket in position as shown in Fig. 5.59. 3. Remove bolts 1 and tap pins 2 out. 4. Move away with the machine or lift the boom. 5. Protect disassembled O-rings 3 and 1.5 mm shims 4. 6. Reinstall the bucket in the reverse order. IMPORTANT: Allowable gap between bucket supports and boom arms is 1.5 mm. If gaps are bigger, fill symmetrically with shims. WARNING! When replacing the bucket take care. Disassembled heavy compo- nents of loader linkage system (boom arms, connector) must be securely protected against sudden movement.

OM560C99/1E DRESSTA