Mitsubishi Heavy Industries — FUEL SYSTEM

(3) Remove nozzle tip (3), distance piece (4), pres- sure pin (5), spring (6) and washer (7) from nozzle holder. (4) All the parts disassembled should be washed in clean kerosene and dried with compressed air. Decar- bon the nozzles removed with a wooden scraper and clean them thoroughly in gasoline. 5-3 Inspection (1) Needle valve and nozzle body (a) Immerse needle valve and nozzle body in a pool of clean kerosene, insert the valve into the body, and move the valve back and forth to be sure that the sliding contact is smooth without evidencing any excessive clearance.

The injec- tion nozzle as a whole must be replaced if the fit is found defective_ (b) Visually examine the nozzle body with a magn. fying glass having a power of 4 or 5. (c) Inspect the needle valve for distortion or dam- age at its seating part and for wear of its end face in contact with the pressure pin. (d) Poor seating contact may be corrected, if the defective condition is not advanced too far, by lapping the valve against the seat with a coat of clean lube oil applied to the seating faces. If this does not help, the injection nozzle must be replaced. (2) Nozzle holder and distance piece Check the fit between nozzle holder and distance piece.

Determine the quality of the fit from contact patterns obtained with the use of red lead paste: defective fit will be evidenced by an abnor- mally high rate of return oil (leak-ofQ flow. (3) Pressure spring and pressure pin (a) Replace any pressure spring broken, cracked or otherwise defective, or out of square. Inspect each spring for these defects. (b) Inspect each pressure pin for wear at its end faces, one for pressure spring and the other for needle valve: (4) Leak-off pipe packing If the packing is found in deteriorated condition, replace it. -61-