hyundai — 2. MAIN CONTROL VALVE

Boom down operation During the boom down operation, the pilot secondary pressure from the RCV is supplied to the against port of the spring side and shifts the boom 1 spool to the right direction. The P1 bypass passage is shut off by the movement of the boom 1 spool and the pressurized oil from P1 port is entered P1 parallel passage and then passes through the load check valve and bridge passage then flows into the rod side of the boom cylinder via Bb port. At the same time, the return oil from head side of the boom cylinders flows the boom 1 spool through the Ab port and the boom holding valve and return to the hydraulic oil tank through the tank passage.

At this time, some of the return oil from the boom head side passes to the connected passage of the boom 1 spool inside and flows into the P1 parallel passage. (Boom spool inside regeneration function). At this time, the boom holding valve is open status and the operation principles are described following page. During the boom down operation, the flow is not combined. (2) Holding valve release signal RCV signal Tank passage Boom 1 Swing C-C' (SWING AND BOOM1) 220S2MC23 2-37 rod side Bb Cylinder head side RCV signal Ab