OPERATION INCREASING TRACK GAUGE 1. Remove center frame mounting bolts (1) front and rear, 4 each from the front and rear of the track frame on the side to be extended. 2. Swing the upper structure to the side where the track frame gauge is to be increased, set it at 90 o to the track frame (2), then use the work equipment to jack up the track frame. Remark Height (H) of the track frame being raised should be less than 50 mm (2 in). Take care not to raise the track so much that the stopper bolt is distorted. 3. Using the arm, pull the machine to the front. The track frame will slide. 4.
Extend the track frame until it comes into contact with the stop- per, then lower the machine slowly to the ground. Install bolts (1) front and rear 9 each and tighten to specified torque. Tightening torque: 1520 to 1910 Nm (1121 to 1410 ft/lbs) 5. Follow the same procedure to retract the track frame on the other side. PC400LC-7E0 2-133