Hitachi Construction Machinery — Removal and Installation of Pilot Shut-Off Valve

BODY (UPPERSTRUCTURE) / Pilot Shut-Off Valve REMOVAL AND INSTALLATION OF PILOT SHUT-OFF VALVE 2 3 CAUTION: Bleed air from the hydraulic oil tank before doing any work. (Refer to BLEED AIR FROM HYDRAULIC OIL TANK on W1-4-1.) Removal 1. Remove screws (2) (2 used) from cover (3). Remove cover (3) from bracket (6). 2. Remove sems bolts (11) (4 used) from cover (10). Remove cover (10) from bracket (6). 4 7 5 6 8 9 1 10 : 13 mm 3. Remove spring (8) from block (7) and bracket (9). 4. Remove bolt (1) from lever (4). Remove lever (4) from block (5). 11 : 14 mm 5. Disconnect hoses (12, 15, 16 and 17) from pilot shut-off valve (14). Cap the open ends. 12 13 W4GB-02-07-001 14 : 19 mm, 22 mm 6.

Remove bolts (13) (2 used) from the cockpit. Remove pilot shut-off valve (14) from the cockpit. : 17 mm 15 W4GB-02-07-002 17 16 W4GB-02-07-003 W2-9-1