Kenworth — Kenworth T170 T270 T370 and Hybrid 2011 Body Builders Manual

Section 4 Exhaust & Aftertreatment Figure 4-3: Orientation of Dosing Module Right Hand Under DPF and SCR with Rectangular Small or Medium DEF Tanks Figure 4-4: RH Under Cab Exhaust with Small or Medium Tanks. The height differential between the supply module and dosing module can not exceed one meter. The supply module is integrated into the DEF tank assembly, separation of the module from the tank is not allowed. When relocating the components the maximum pressure DEF hose length, from Supply module to Dosing Module, is 3 meters (118”). DEF Pressure hose must include a “trap” in the routing if Dosing Module is below the highest point of the Supply Module (See Figure 4-8 on page 4-8).

4-5 12/11